KUTHEER INFRAA · Medchal-Malkajgiri · RERA P02200002278

KUTHEER is a residential apartment project in Uppal, Uppal mandal, Medchal-Malkajgiri district, developed by registered promoter KUTHEER INFRAA. The project is on 501.64 sq. m of land and comprises one residential building with 1 Stilt + 5 upper floors and 10 3 BED ROOM apartments, each with a saleable area of 97.33 sq. m. It is registered with TG-RERA under **P02200002278**, and its proposed completion date is **01/06/2021**.

More from Kutheer Infraa · 2 projects →

01What we found

Period endedTG-RERA registration ran to 1 Jun 2021 - check its extension on TG-RERA
8documents on file - each fact links to its page
0court cases on this project's land in the court records searched
11items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

11 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameKUTHEER RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionNo phase name is disclosed. The registration is for the project KUTHEER; the filed building approval describes one apartment building. RERA record
TG-RERA registrationP02200002278, granted under section 5; issued 31/10/2020, valid from 31/10/2020 to 01/06/2021. The supplied certificate records no extension. Registration validity is separate from the completion date and occupancy status. RERA record
Registered promoterKUTHEER INFRAA; the RERA record identifies the organisation type as Partnership. RERA record RERA filing
RERA statusRecorded as On-Going Project in the project information. RERA filing

Land and geographic identity

FieldProject record
LocalityUppal RERA record RERA filing
Revenue villageUppal Bagayath / Uppal Bhagath Village appears in the project and approval records; the exact village naming is preserved here as recorded. RERA record Land records
Mandal / district / PINUppal, Medchal-Malkajgiri, 500039 RERA record RERA filing
Project survey numbers and subdivisions1 to 40; 282 to 368; 369 (P); 370 to 373; 374 (P); 375 to 387; 395 to 401; 454; 456 to 459; 505(P); 510 to 564. The HMDA approval extraction prints these as 1TO40; 282TO368; 369(P); 370TO373; 374(P); 375TO387; 395TO401; 454; 456TO459; 505(P); 510 TO 564.
Registered site extent501.64 sq. m in the RERA land details. The HMDA technical approval states 501.67 Sq. Mt. Land records
Total / net area and affected areaRERA land record: total area 501.64 sq. m, net area 501.64 sq. m, affected area 0.0 sq. m. Land records
BoundariesNorth: Plot No. 944; South: Plot No. 942; East: 18 M ROAD; West: Plot No. 934. Land records

Development identity

FieldProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA); the approval states technical approval, with building plans to be sanctioned and released by the Executive Authority. Approvals record
Principal approvalHMDA approval/application number 020720/GHT/R1/U6/HMDA/21022019, dated 04/09/2019. Approvals record
RERA-filed plan approval number020720/GHT/R1/U6/HMD RERA record RERA filing
Approved built-up areaThe approval extraction lists Built up Area 1102.1 and Proposed Built-up Area 1322.52; the supplied record does not explain the distinction between those entries.
Building count and configurationOne residential building; 1 Stilt + 5 upper floors, as described in the HMDA technical approval. RERA filing
Height14.99 is stated in the approval’s sanctioned parameters; the supplied extraction does not specify the unit.
Parking / mortgage provisionApproval records 122.15 Sq.mts as mortgage area, described as 11.08% of built-up area on the first floor, in favour of MC, HMDA. A parking count or parking-level plan is not disclosed in the supplied evidence. RERA filing
Unit countThe RERA land-details entry records 1 total building unit and 1 proposed building unit; the unit filing separately lists 10 apartments. The meaning of the “building units” field is not further explained in the supplied record. RERA filing RERA unit table RERA unit details

Offering and status

FieldProject record
Unit type3 BED ROOM / 3BHK apartments RERA unit table RERA unit details
RERA-filed saleable area97.33 sq. m per unit RERA unit table RERA unit details
RERA-listed inventory10 units; 0 booked, 10 available. The portal-derived counts have no stated as-of date and are indicative. RERA unit table RERA unit details
Construction stage / declared progressProject record says On-Going Project and shows completeness of 90%; this is a recorded figure, not an independently verified site inspection. RERA filing RERA record
Completion datesOriginal proposed completion: 01/06/2021; revised proposed completion: 01/06/2021. These are completion-deadline entries, not evidence of completion or an occupancy certificate. RERA record RERA filing
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied project documents. The HMDA approval states an occupancy certificate is compulsory before occupation and requires the applicant to approach HMDA after completion. Document index

2. The project story

KUTHEER is recorded with TG-RERA as a residential apartment project in Uppal, Medchal-Malkajgiri district. Its filed land record describes a site of 501.64 sq. m, bounded by Plots 944, 942 and 934 and an 18 M road; the HMDA technical approval identifies Plot No. 943 and describes one residential building. The site extent and boundaries are recorded above. RERA record Land records

The RERA unit record lists ten 3-bedroom apartments, each with a filed saleable area of 97.33 sq. m. It shows no units booked and ten available, but the portal-derived inventory has no stated as-of date. The project information labels the development ongoing and reports 90% completeness; that figure is a project-record declaration, not independent verification of construction progress. RERA unit table RERA unit details RERA filing RERA record

The registration certificate runs from 31/10/2020 to 01/06/2021 and records no extension. The project record gives 01/06/2021 as both the original and revised proposed completion date. No occupancy or completion certificate is present in the supplied evidence, so completion and permission to occupy are not established by these records. RERA record Document index

3. Master plan, architecture & building design

The RERA record identifies a single building and the HMDA technical approval describes a residential building named N (KUTHEER INFRA) with 1 Stilt + 5 upper floors. The approval gives a height of 14.99 (unit not stated) and lists approved-parameter entries of Built up Area 1102.1 and Proposed Built-up Area 1322.52. These are reported as stated; the supplied approval extraction does not define their respective measurement bases. RERA filing

The approval names Plot No. 943 and lists the project survey numbers and subdivisions in the land-identity table above. No drawing-derived information is supplied for the building footprint, flats per floor, lifts, stairs, entries, internal circulation, landscaping, open-space arrangement or residential/common-area distribution. The supplied floor-plan record contains one drawing, but no flats were measured from it. Floor plans

The approval includes conditions concerning rainwater-harvesting structures, a transformer and a garbage house, and states that plans are to be sanctioned and released by the Executive Authority in conformity with HMDA’s technical approval. This section does not establish that those works have been completed.

4. Homes, configurations & floor plans

The RERA filing lists ten units as 3 BED ROOM, with 0 booked and 10 available, and a saleable area of 97.33 sq. m. The booking counts have no as-of date in the supplied record. RERA unit table RERA unit details

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3 BED ROOM / 3BHK1001097.33 sq. mNot measured from the supplied drawingNot supplied

The floor-plan evidence says its measurements would be software-measured from approved drawing geometry and would not be RERA disclosures; however, the supplied drawing record shows 0 measured and no flats identified. No carpet-area figure, room dimensions, orientation, balcony or utility-area measurements are therefore available here. Saleable area is the RERA-filed figure; the supplied evidence provides no project-specific calculation of carpet area or common-area loading. Floor plans RERA unit details

5. Parking & vehicle circulation

The HMDA approval records 122.15 Sq.mts of mortgaged built-up area, described as 11.08% of built-up area on the first floor, in favour of MC, HMDA. This is a mortgage provision, not a stated count of resident or visitor parking spaces. RERA filing

No sanctioned parking count, two-wheeler provision, accessible or visitor spaces, parking layout, ramps, internal driveways, EV charging or unit-wise parking allocation is established in the supplied evidence. The development-agreement record refers to five car parkings in each party’s allocation, but does not provide a parking plan or establish a particular buyer’s exclusive allocation. Parties record

6. Amenities, recreation & open spaces

The HMDA approval names rainwater-harvesting structures, a transformer and a garbage house as conditions or required provisions. The RERA amenities record contains 14 listed infrastructure/amenity categories, but each shows 0% progress; Water Supply, Sewerage and Storm Water Drains are marked “YES” in the record. These entries do not establish completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Rainwater harvestingStructures required by the HMDA approval; no size or capacity suppliedApproval condition; completion not established
TransformerProvision required within the premises; no capacity suppliedApproval condition; completion not established
Garbage houseProvision required within the premises; no size suppliedApproval condition; completion not established
Internal roads & footpathsNo dimensions suppliedRERA amenities0% recorded
Water supplyNo source, storage or capacity suppliedRERA amenitiesMarked “YES”; 0% recorded
Sewerage / STPNo treatment capacity or reuse details suppliedRERA amenitiesMarked “YES” for sewerage; 0% recorded
Storm-water drainsNo dimensions or capacity suppliedRERA amenitiesMarked “YES”; 0% recorded
Green strip / tot lot / parkNo area or facility detail suppliedRERA amenities0% recorded
Street lightingNo fixture or coverage details suppliedRERA amenities0% recorded
Community buildingsNo building or size details suppliedRERA amenities0% recorded
Sewage and sullage treatment/disposalNo system details suppliedRERA amenities0% recorded
Solid-waste management and disposalNo system details suppliedRERA amenities0% recorded
Water conservation / rainwater harvestingNo size or capacity suppliedRERA amenities0% recorded
Energy managementNo system details suppliedRERA amenities0% recorded
Fire protection and fire safetyNo system details suppliedRERA amenities0% recorded
Electrical meter room / substation / receiving stationNo size or capacity suppliedRERA amenities0% recorded
Recreational open spaceNo area suppliedRERA amenities0% recorded

The separate vendor record lists additional features such as indoor games, a kids’ play area, power backup, security and a park/central green, but these are vendor-reported, not established here as RERA-filed or delivered facilities. Promoter website

7. Utilities, building services & safety

The RERA amenities record marks Water Supply, Sewerage and Storm Water Drains “YES,” while recording 0% progress for each listed category. It does not specify water sources, storage, treatment capacity, sewerage-treatment capacity, reuse, storm-water design or harvesting capacity. RERA amenities

The HMDA approval requires rainwater-harvesting structures, a transformer and a garbage house within the premises. The RERA amenities record separately lists energy management, fire protection and fire-safety requirements, an electrical meter room/substation/receiving station, and solid-waste management and disposal, each with 0% progress recorded. No service capacities, lift details, backup systems, CCTV/access-control arrangements, accessibility provisions or fire-system specifications are supplied. RERA amenities

The approval also requires a completion notice after building completion and an occupancy certificate before occupation. The supplied documents do not include evidence that these steps have been completed. Document index

8. Location, access & connectivity

The registered project location is Uppal, Uppal mandal, Medchal-Malkajgiri district, Telangana, PIN 500039. The project record gives the site address as Plot No. 76, building name SRI NILAYAM, Bathuakamakunta, beside Gokul Sweet House Lane, Uppal; the HMDA approval identifies Plot No. 943. RERA record RERA filing

The recorded site boundaries identify an 18 M ROAD on the east, with Plot No. 944 to the north, Plot No. 942 to the south and Plot No. 934 to the west. No project-specific approach-road plan or public-transport details are supplied. Land records

No distances or travel times to transport, services or landmarks are established in the project’s supplied official location records. Vendor-reported connectivity claims are not used as verified location measurements in this overview.

9. Developer & development status

The registered promoter is KUTHEER INFRAA, identified in the RERA project record as a partnership. GADE SABITHA is listed as an authorised signatory. The supplied record does not provide a verified registered office address, contact details, website or a corporate registration identifier; a masked identifier appears in the project fields but is not labelled. Corporate record Parties record RERA filing

The project information records 90% completeness and an ongoing-project status; the evidence does not include an independent site inspection confirming that progress. The proposed completion date is 01/06/2021, and the RERA certificate records validity through 01/06/2021 without an extension. No occupancy or completion certificate is present in the supplied documents. RERA record RERA filing Document index

The RERA record identifies a revenue-share arrangement with KUTHEER INFRA as landowner and records one development agreement. It describes a 50% share for the landowners and 50% for the developer, allocated by flats and car parking. Parties record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02200002278; issued 31/10/2020; valid to 01/06/2021
What the supplied record establishesForm C registration for KUTHEER under section 5; supplied certificate records no extension.
HMDA technical building approval
Identifier / date020720/GHT/R1/U6/HMDA/21022019; 04/09/2019
What the supplied record establishesTechnical approval for a residential apartment building identified as N (KUTHEER INFRA), with 1 Stilt + 5 floors; includes conditions for the Executive Authority’s sanction/release of building plans.
RERA-filed plan approval reference
Identifier / date020720/GHT/R1/U6/HMD
What the supplied record establishesPlan approval number entered in the project information. RERA record RERA filing
Registered mortgage deed reference in approval
Identifier / date10959/2019, dated 18/7/2019; also printed as 10959 of 2019, dated 18.07.2019
What the supplied record establishesApproval extraction refers to a mortgage of 122.15 sq. m of built-up area, described as 11.08% on the first floor, in favour of MC, HMDA.
Development agreement / supplemental deed
Identifier / dateDocument No. 3079/2020; RERA document record identifies the supplemental deed
What the supplied record establishesRecords the 50:50 landowner/developer allocation and refers to the earlier Development Agreement-cum-GPA, Document No. 9250/2018. Parties record
Title deed
Identifier / dateConveyance Deed 4480/2018, dated 06/03/2018
What the supplied record establishesRERA-filed title report describes HMDA’s conveyance of Plot No. 943, measuring 600 Sq.Yards, to Smt. Boggavarapu Gopi Kumari. Land records
Form B declaration
Identifier / dateDocument 126461
What the supplied record establishesPromoter declaration includes title-basis, encumbrance, completion, funds, audit and approvals statements; no project registration number is stated in the extracted declaration.
Layout plan / layout approval
Identifier / dateDocument 115855
What the supplied record establishesThe supplied record requests a stamped layout approval or layout plan, or a declaration/equivalent document; extraction is unavailable, so an approved layout drawing is not established here. Document index
Occupancy / completion certificate
Identifier / dateNot present in supplied document set
What the supplied record establishesThe HMDA approval requires an occupancy certificate before occupation; no issued certificate is included in the supplied records. Document index

The supplied floor-plan material contains one drawing record but no measured flats, and no occupancy/completion certificate is included in the supplied documents. These are limits of the evidence reviewed for this overview. Floor plans Document index

Frequently asked questions

Is KUTHEER registered with Telangana RERA?

Yes. KUTHEER is registered with the Telangana Real Estate Regulatory Authority as P02200002278; the registration status is On-Going Project.

Who is the developer of KUTHEER?

The promoter named in the RERA registration is KUTHEER INFRAA.

Where is KUTHEER located?

KUTHEER is in UPPAL, Medchal-Malkajgiri, Telangana (500039).

When will KUTHEER be completed?

The promoter's proposed date of completion filed with RERA is 01/06/2021. This is the promoter's declaration, not a guarantee.